October 31, 2022
Construction on all five bridges along the lagoon path will begin on September 9, 2022 and will be completed in early December. Detour routes will be posted at each bridge. A section of the Community parking lot will also be closed for construction materials.
The construction schedule is as follows:
- Bridge 4: 9/9 – 9/21 (BIP – Sea Bridge & Moss Point) – COMPLETED
- Bridge 3: 9/22 – 10-7 (BIP – Water’s Edge & Sand Harbor) – COMPLETED
- Bridge 2: 10/10 – 11/1 (BWV/CCV – Ironwood Road & Capetown Drive) – COMPLETED
- Bridge 1: 11/2 – 11/16 (CBR/CCV – Jervis Bay & Channing Way) – COMPLETED
- Bridge 5: 11/17 – 12/9 (COL/WDB – Anderson Road & Kofman Parkway) – COMPLETED
Please click here for a map of bridge locations.
Questions should be directed to Joe Landaeta, Director of Maintenance, at jlandaeta@harborbay.org or 510-865-3363 ext. 350.